3 corrections found
a more direct connection via the Champlain Hudson Power Express HVDC line is expected to come online in 2025.
This is outdated: the Champlain Hudson Power Express did not come online in 2025. The project’s official site says it became operational on May 13, 2026.
Full reasoning
The article says the CHPE line was expected to come online in 2025. The project’s official construction page now states that all major construction work was completed in January 2026 and that CHPE became operational on May 13, 2026. That directly contradicts the 2025 in-service date stated here.
Because this claim is about a specific project timeline, the current official project status is the strongest evidence. The statement may have been accurate as an earlier expectation, but as written now it is no longer correct.
1 source
- Construction - TDI CHPExpress
Construction of the Champlain Hudson Power Express (CHPE) began on November 30, 2022, and all major construction work was completed in January 2026 ... CHPE became operational on May 13, 2026.
through its seven power plants
Con Edison’s own steam page says its steam is generated at five steam-generating plants, with additional steam supplied under contract from the Brooklyn Navy Yard—not seven Con Edison power plants.
Full reasoning
The article says Con Edison produces steam through its seven power plants. Current Con Edison source material says otherwise: "The vast majority of our steam ... is made ... in one of our five steam-generating plants" and adds that the company also receives steam "under contract from the Brooklyn Navy Yard." The same page breaks that down as 4 plants in Manhattan, 1 plant in Queens, and 1 plant delivering steam under contract in Brooklyn.
So the current system is not seven Con Edison-operated power plants. It is five steam-generating plants operated by Con Edison, plus one contracted supplier in Brooklyn.
1 source
- How We Source Our Steam | Con Edison
The vast majority of our steam (over 97 percent) is made from burning natural gas in one of our five steam-generating plants. We also get it delivered under contract from the Brooklyn Navy Yard. ... Manhattan 4 plants ... Queens 1 plant ... Brooklyn 1 plant delivering steam under contract.
Over five million electric and gas meters were replaced in this project.
This overstates the size of the rollout. Con Edison says it has installed nearly five million smart meters, and a New York DPS filing says about 4.85 million had been deployed as of June 2024.
Full reasoning
The article says over five million electric and gas meters were replaced. Current Con Edison materials say "We've installed nearly five million smart meters", which is below five million. A New York Department of Public Service filing from Con Edison is more specific: it says that as of June 2024, Con Edison had successfully deployed approximately 4.85 million AMI meters.
Those official figures contradict the article’s claim that the project replaced over five million meters.
2 sources
- All About Con Edison Smart Meters | Con Edison
We've installed nearly five million smart meters, which provide more information about how you use energy so you can make better energy decisions.
- Con Edison AMI Stabilization and Optimization Filing (New York Department of Public Service)
As of June 2024, Con Edison has successfully deployed approximately 4.85 million AMI meters ... As of the end of June 2024, Con Edison has successfully installed approximately 4.85 million meters across its service territory.